Coronavirus (COVID-19) Updates: What You Need to Know. LEARN MORE

Parking

The AnMed Health parking deck was scheduled for repairs beginning in late June. The 30-year old parking deck at the Medical Center needed repairs for damage to the surface coating, which caused leaks and deterioration of the concrete. In order to ensure continued safe and convenient parking for our patients and visitors, AnMed Health launched a multi-phase deck repair project.

Patients are currently asked to park following the appropriate lanes. Parking is allowed in the non-fenced areas. An earplug dispenser station was also placed on a column at the breezeway of the level B parking deck. We appreciate your patience and understanding as we complete this important construction.

Parking Deck Four-Phase Construction Plan

Phase 1 (Aug 2019 - May 2020)
Demolition of protective barrier wall

Phase 2 (May 2020 - Oct 2020)
Surface coating of 75 parking spaces on top deck

Phase 3 (Oct 2020 - February 2021)
More concrete replacement and resurfacing. Bricks above the B level entrance on North Street are being replaced.

Phase 4 (March 2021 - June 2021)
Continuation and completion of concrete replacement